Construction of single storey building with 9-11m high free-form landscape terraced roof garden, over sewage treatment faculties, including 12m deep balancing tank and other treatment and management facilities.
Appointment by Contractor for the DfMA study and design to simply the structural layout and the construction method with usage of precast / semi-precast construction method.
DfMA implementation includes the deletion of one layer of beams at high level , and replacement some of the in-situ 1.5m RC beams partly by precast hollow box section, substantially increasing the efficiency of construction.