We were employed by HyD in June 2019 for this Assignment under the Third Phase of the UAP, including provision of UAF as well as associated works for 48 Walkways located in New Territories (North, Sha Tin, Tai Po and Yuen Long Districts). The priority task is to ascertain the feasibility and obtain the consensus from maintenance and management parties particularly non-Hyd walkways including legal agreement, during the Investigation Phase. To promptly arrange pre-construction works contract to identify utilities, TTA trial runs will be conducted for affirming the lift locations. Other tasks are to carefully conduct public/DC consultation taking care of the coming DC election period and ensure approval of ACABAS for our designs. We have to be carried out in a fast track manner aiming at commencing the Early Construction Walkways in 2020 for completion and commission by 2023. The first Remaining Walkways shall commence by 2021 for completion and commission by 2024 and the second Remaining Walkways shall commence by 2022 for completion and commission by 2026.